Commercial HVAC Retrofit: Rooftop Unit Upgrade
Retrofitting aging HVAC equipment in a retail complex while addressing voltage drop issues that had plagued the original installation for years.
Voltage drop reduced from 6.2% to 2.4%
HVAC efficiency improved 18%
Eliminated compressor short-cycling
Reduced maintenance costs 40%
Challenge
Replacing 15-year-old rooftop units with modern equipment while fixing chronic voltage drop issues
Solution
Feeder upgrade and strategic sub-panel placement reduced voltage drop from 6.2% to 2.4%
Project Overview
A 120,000 square foot retail complex in Atlanta, Georgia had experienced chronic HVAC problems for over a decade. The building housed 12 tenant spaces, each with its own rooftop HVAC unit, totaling 150 tons of cooling capacity. Property management had replaced compressors multiple times, dealt with constant service calls, and faced frustrated tenants complaining about inadequate cooling during summer months. When the decision was made to replace the aging equipment with new high-efficiency units, the electrical contractor conducted a thorough analysis that revealed the root cause of the problems: severe voltage drop in the original electrical installation.
The original electrical design, installed 25 years earlier when the building was constructed, used minimal conductor sizes that met code requirements at the time but provided inadequate voltage to the rooftop equipment. With runs of 300+ feet from the main electrical room to the roof, the undersized conductors resulted in voltage drop approaching 8% during peak cooling demand. This low voltage caused compressors to run hot, start hard, and fail prematurely.
This case study examines how the retrofit project addressed both the equipment replacement and the underlying electrical issues, resulting in a dramatic improvement in system performance and reliability.
Diagnosing the Problem
Original Installation Issues
- • Conductor Size: #8 AWG copper for 40A circuits
- • Run Length: 280-350 feet to rooftop units
- • Measured Voltage: 198-205V at units (nominal 240V)
- • Voltage Drop: 6.2% average, 7.8% during startup
- • Compressor Impact: Drawing 15-20% higher current to compensate
The voltage measurements revealed a chronic undervoltage condition. When voltage to a compressor is low, the motor must draw higher current to produce the required power output. This creates a destructive cycle: higher current causes additional I²R heating in the motor windings, which accelerates insulation breakdown and leads to premature failure. The higher current also increases voltage drop in the already undersized conductors, making the problem even worse during peak demand periods.
The Solution: Rooftop Sub-Panel
The engineering team evaluated two approaches: replacing the individual circuit conductors with larger sizes, or installing a sub-panel on the roof with a single large feeder from the main distribution. The sub-panel approach proved more cost-effective and provided superior voltage drop performance.
New Installation Design
- • Main Feeder: 400A, parallel 3/0 AWG copper to roof
- • Feeder Length: 300 feet (single optimized run)
- • Feeder Voltage Drop: 1.8% at full load
- • Branch Circuits: #6 AWG, maximum 50ft runs
- • Branch Voltage Drop: 0.6% maximum
- • Total Voltage Drop: 2.4% maximum
Results and Benefits
Performance Improvements
- • Voltage drop: 6.2% → 2.4%
- • Measured voltage: 234V average
- • HVAC efficiency: +18%
- • Compressor current: -15%
- • Operating temperature: -20°F
Economic Benefits
- • Annual energy savings: $24,000
- • Maintenance reduction: 40%
- • Extended equipment life: 5+ years
- • Tenant satisfaction: Improved
- • Payback period: 3.2 years
Evaluate Your HVAC Circuits
Experiencing HVAC reliability issues? Voltage drop might be the hidden cause. Use our calculator to evaluate your existing installations and plan upgrades.
Check Your CircuitsRelated Case Studies
Industrial Motor Feeder: 500HP Chiller Installation
Engineering a 500HP chiller motor feeder with voltage drop optimization for a manufacturing facility, balancing starting current requirements with running efficiency.
AgriculturalAgricultural Irrigation: Remote Pump Station Design
Engineering power distribution for a 500-acre farm irrigation system with pump stations located up to 2,000 feet from the main electrical service.