Illustrative example · Commercial

This is an illustrative engineering example built from stated assumptions, not a record of a specific installed project.

Commercial HVAC Retrofit: Rooftop Unit Upgrade

Hypothetical setting: Atlanta, GA

Assume a 240V single-phase rooftop load of 40A on a 300ft one-way 8 AWG copper circuit. Compare it with a rooftop-panel arrangement using an assumed 400A feeder load and a shorter branch circuit.

Original branch assumption

18.67 V · 7.78%

New shared feeder assumption

3.10 V · 1.29%

New rooftop branch assumption

1.96 V · 0.82%

New arrangement, feeder + branch in series (240 V base)

5.06 V · 2.11%

Conditions: compared path is service to rooftop unit. The new arrangement is the feeder plus rooftop branch in series, both at the same 240V base; loads are stated assumptions, resistive model at unity power factor.

Challenge

Distinguish calculated conductor drop from unverified voltage measurements.

Comparison approach

Compare the original branch with a 300ft feeder of two parallel 500 kcmil sets plus a 50ft, 6 AWG branch. Add the two new segment drops at the same voltage base.

Stated inputs and calculation method

All lengths below are one-way feet. Resistance R is in Ω per 1000ft from the site’s 75°C resistance table. N is the number of identical parallel sets. The AC examples use a resistive estimate at unity power factor, without reactance or source impedance.

DC / single-phase: Vd = 2 × I × L × R / (1000 × N). Three-phase: Vd = √3 × I × L × R / (1000 × N).

Vd% = Vd / V × 100; load voltage = V − Vd.

Results are calculated before rounding; displayed voltages and percentages use two decimal places. These are conductor-drop estimates, not field measurements or full installation approvals.

Site wire tables

Worked voltage-drop comparisons

Original branch assumption

240 V · I = 40 A · L = 300 ft · 8 AWG · copper · N = 1

Table resistance: R = 0.778 Ω/1000ft; R/N = 0.778 Ω/1000ft.

Vd = 2 × 40 × 300 × 0.778 / (1000 × 1) = 18.67 V

Vd% = 18.67 / 240 × 100 ≈ 7.78%

Calculated load voltage: 240 − 18.67 = 221.33 V

New shared feeder assumption

240 V · I = 400 A · L = 300 ft · 500 kcmil · copper · N = 2

Table resistance: R = 0.0258 Ω/1000ft; R/N = 0.0129 Ω/1000ft.

Vd = 2 × 400 × 300 × 0.0258 / (1000 × 2) = 3.10 V

Vd% = 3.10 / 240 × 100 ≈ 1.29%

Calculated load voltage: 240 − 3.10 = 236.90 V

New rooftop branch assumption

240 V · I = 40 A · L = 50 ft · 6 AWG · copper · N = 1

Table resistance: R = 0.491 Ω/1000ft; R/N = 0.491 Ω/1000ft.

Vd = 2 × 40 × 50 × 0.491 / (1000 × 1) = 1.96 V

Vd% = 1.96 / 240 × 100 ≈ 0.82%

Calculated load voltage: 240 − 1.96 = 238.04 V

New feeder + branch total: 3.096 + 1.964 = 5.060 V; 2.11%; load voltage = 234.940 V.

Engineering interpretation and limits

This example uses calculated voltages only. It does not treat the previously quoted field voltages as measurements from a real project.

The feeder and branch loads are independent stated assumptions. For a real rooftop panel, calculate the combined equipment load and check each unit’s nameplate minimum circuit ampacity and maximum protection rating.

Shorter branches and lower feeder resistance can reduce drop. This comparison does not predict compressor efficiency, maintenance, equipment life or tenant satisfaction.

Economic evaluation requires real inputs

Any savings estimate needs actual electricity prices, operating hours and the load profile. Installed cost, maintenance and equipment life need project evidence. No savings amount, payback period or customer outcome is claimed for this example.

Apply the method to your inputs

Enter the actual voltage, current, one-way distance, conductor and parallel sets. Check voltage drop together with ampacity, correction factors, protection and equipment requirements.

Open Calculator

Related illustrative examples