Illustrative example · Renewable

This is an illustrative engineering example built from stated assumptions, not a record of a specific installed project.

Solar Farm DC Collection: Optimizing Energy Harvest

Hypothetical setting: Mojave Desert, CA

Assume a PV string operating at 1020V DC and 11.8A, with a 500ft one-way home run. Both language versions use the same hypothetical Mojave Desert, California setting.

10 AWG string home run

14.63 V · 1.43%

8 AWG string home run

9.18 V · 0.90%

Challenge

Compare resistive DC drop for two string conductor sizes at a stated operating point.

Comparison approach

Calculate the complete outgoing-and-return loop for 10 AWG and 8 AWG copper.

Stated inputs and calculation method

All lengths below are one-way feet. Resistance R is in Ω per 1000ft from the site’s 75°C resistance table. N is the number of identical parallel sets. The AC examples use a resistive estimate at unity power factor, without reactance or source impedance.

DC / single-phase: Vd = 2 × I × L × R / (1000 × N). Three-phase: Vd = √3 × I × L × R / (1000 × N).

Vd% = Vd / V × 100; load voltage = V − Vd.

Results are calculated before rounding; displayed voltages and percentages use two decimal places. These are conductor-drop estimates, not field measurements or full installation approvals.

Site wire tables

Worked voltage-drop comparisons

10 AWG string home run

1020 V · I = 11.8 A · L = 500 ft · 10 AWG · copper · N = 1

Table resistance: R = 1.24 Ω/1000ft; R/N = 1.24 Ω/1000ft.

Vd = 2 × 11.8 × 500 × 1.24 / (1000 × 1) = 14.63 V

Vd% = 14.63 / 1020 × 100 ≈ 1.43%

Calculated load voltage: 1020 − 14.63 = 1005.37 V

8 AWG string home run

1020 V · I = 11.8 A · L = 500 ft · 8 AWG · copper · N = 1

Table resistance: R = 0.778 Ω/1000ft; R/N = 0.778 Ω/1000ft.

Vd = 2 × 11.8 × 500 × 0.778 / (1000 × 1) = 9.18 V

Vd% = 9.18 / 1020 × 100 ≈ 0.90%

Calculated load voltage: 1020 − 9.18 = 1010.82 V

Engineering interpretation and limits

The stated operating voltage and current are assumptions for this comparison. Actual string sizing also needs module open-circuit voltage, short-circuit current, temperature limits and equipment ratings.

For a combiner, add the currents of the connected strings before checking the downstream conductors. Do not reuse a single-string current for the combined circuit.

A drop at one operating point does not determine annual energy yield or PPA revenue. Revenue and payback require an actual generation profile, tariff and installed cost.

Economic evaluation requires real inputs

Any savings estimate needs actual electricity prices, operating hours and the load profile. Installed cost, maintenance and equipment life need project evidence. No savings amount, payback period or customer outcome is claimed for this example.

Apply the method to your inputs

Enter the actual voltage, current, one-way distance, conductor and parallel sets. Check voltage drop together with ampacity, correction factors, protection and equipment requirements.

Open Calculator

Related illustrative examples