Underground Feeder Voltage Drop: Burial Depth, Wire Size, and NEC 300.5 Planning
Size underground feeders with real voltage-drop math, NEC 300.5 cover rules, conductor material choices, derating checks, and practical examples for garages, barns, pumps, and remote panels.
An underground feeder is a buried branch or feeder circuit that carries power from one building, service equipment, or distribution point to remote equipment such as a garage, barn, pump house, gate operator, pool pad, or detached workshop. It looks simple on a site plan, but the installed route usually adds trench bends, risers, sweeps, building offsets, and future load assumptions that make voltage drop more important than the first ampacity lookup suggests.
This guide is written for electricians laying out trenches, engineers reviewing feeder schedules, and DIY users trying to understand why a legal conductor can still leave a remote panel weak. The code questions and the performance questions are separate. NEC 300.5 tells you about minimum cover for underground wiring methods. NEC 310.16 and 310.12 help with conductor ampacity in common conditions. NEC 215.2(A)(1) and 210.19(A)(1) informational notes point designers toward the familiar 3% feeder or branch and 5% total voltage-drop targets. The buried feeder has to survive all of those checks at the same time.
Workshop: 1 AWG aluminum, 240 V, 80 A and 184 ft one way. R = 0.253 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 80 × 184 × 0.253 / 1000 / 1 = 7.44832 V; 100 × 7.44832 / 240 ≈ 3.10347%. Check the margin for downstream circuits and the installation conditions. Workshop, larger conductor: 2/0 AWG aluminum, 240 V, 80 A and 184 ft one way. R = 0.159 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 80 × 184 × 0.159 / 1000 / 1 = 4.68096 V; 100 × 4.68096 / 240 ≈ 1.9504%. Check the margin for downstream circuits and the installation conditions.
TL;DR
- Underground feeders are sized by ampacity, burial method, voltage drop, and future load margin.
- Use NEC 300.5 for cover depth and NEC 310.16 for conductor ampacity before voltage-drop optimization.
- A 100A, 240V feeder at 180 ft often needs larger conductors than the ampacity minimum.
- Aluminum can be cost-effective underground, but terminations and voltage drop must be checked carefully.
The design baseline in this article is anchored to the National Electrical Code , undergrounding , the International Electrotechnical Commission . Those references matter because code language, conductor physics, and equipment behavior usually fail in the same place: a circuit that was technically legal on paper but poorly optimized for the distance, load, or operating temperature in the field.
What Controls an Underground Feeder Design
The first control is ampacity. A feeder conductor must carry the calculated load after correction and adjustment factors are applied. For dwelling feeders, NEC 310.12 may apply in specific cases, while many detached structures and equipment feeders start with NEC 310.16 and the conductor insulation temperature limits of the terminals. That ampacity pass is necessary, but it is only the beginning.
The second control is burial method. Direct-burial cable, PVC conduit, rigid metal conduit, and residential branch-circuit exceptions can have different minimum cover requirements under NEC 300.5. A feeder that changes wiring method between a building wall, trench, and riser must be detailed correctly at every transition. IEC 60364-5-52 uses different language, but the engineering idea is similar: installation method, thermal environment, mechanical protection, and permissible voltage drop must all be checked before the cable is accepted.
The third control is the voltage-drop budget. A 240V feeder feeding a detached garage might look strong at the source, but a 3% feeder drop is already 7.2V. If branch circuits inside the garage add another 2%, the farthest receptacle or motor is operating around a 5% total drop. That may be acceptable for many loads, but it leaves little margin for compressor starting, EV charging, or utility voltage that is already low at peak demand.
- Measure the installed one-way length. Include horizontal trench length, vertical risers, sweeps, offsets around obstacles, panel locations, and the route inside each building. Voltage drop follows conductor length, not the shortest line on the site plan.
- Confirm burial and protection first. NEC 300.5 cover depth, warning ribbon practice, conduit transitions, and physical protection at risers should be solved before conductor size is finalized.
- Separate neutral and equipment grounding decisions. A detached structure feeder normally needs an insulated neutral isolated from the equipment grounding conductor at the subpanel, with grounding electrode work handled under NEC 250.
- Run feeder drop at realistic demand. Do not size only at breaker rating or only at a tiny present load. A 100A panel may be expected to serve 60A to 80A of real coincident load later.
Comparison Table: Underground Feeder Choices
Hypothetical calculations, not field measurements: the site RESISTANCE_DATA conductor values, referenced to 75°C. R is for one conductor; X = 0, power factor = 1, one set per phase unless the row states two sets. Equal parallel sets divide the result by the set count. L is one-way length. ΔV = 2 × I × L × R / 1000 for DC or single phase; use √3 instead of 2 and line-to-line voltage for balanced three phase. Pair feet with Ω/kft or meters with Ω/km. Drop (%) = 100 × ΔV / V. Only final table results are rounded to two decimals. Source impedance, contacts, unbalance and starting dynamics are excluded; ampacity and local installation requirements need separate review.
| Scenario | Voltage / current | One way | Conductor | R / temperature | Model | Drop |
|---|---|---|---|---|---|---|
| Garage | 240 V / 50 A | 95 ft | 6 AWG Cu | 0.491 Ω/kft; 75 °C | 2; PF = 1 | 4.66 V / 1.94% |
| Workshop | 240 V / 80 A | 184 ft | 1 AWG Al | 0.253 Ω/kft; 75 °C | 2; PF = 1 | 7.45 V / 3.1% |
| Workshop, larger conductor | 240 V / 80 A | 184 ft | 2/0 AWG Al | 0.159 Ω/kft; 75 °C | 2; PF = 1 | 4.68 V / 1.95% |
| Barn | 240 V / 40 A | 260 ft | 2 AWG Al | 0.319 Ω/kft; 75 °C | 2; PF = 1 | 6.64 V / 2.76% |
| Well pump building | 240 V / 30 A | 320 ft | 4 AWG Cu | 0.308 Ω/kft; 75 °C | 2; PF = 1 | 5.91 V / 2.46% |
| EV-ready garage | 240 V / 60 A | 140 ft | 2 AWG Cu | 0.194 Ω/kft; 75 °C | 2; PF = 1 | 3.26 V / 1.36% |
Garage — 6 Cu (1)
Garage: 6 AWG copper, 240 V, 50 A and 95 ft one way. R = 0.491 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 50 × 95 × 0.491 / 1000 / 1 = 4.6645 V; 100 × 4.6645 / 240 ≈ 1.94354%. Check the margin for downstream circuits and the installation conditions.
Workshop — 1 Al (2)
Workshop: 1 AWG aluminum, 240 V, 80 A and 184 ft one way. R = 0.253 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 80 × 184 × 0.253 / 1000 / 1 = 7.44832 V; 100 × 7.44832 / 240 ≈ 3.10347%. Check the margin for downstream circuits and the installation conditions.
Workshop, larger conductor — 2/0 Al (3)
Workshop, larger conductor: 2/0 AWG aluminum, 240 V, 80 A and 184 ft one way. R = 0.159 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 80 × 184 × 0.159 / 1000 / 1 = 4.68096 V; 100 × 4.68096 / 240 ≈ 1.9504%. Check the margin for downstream circuits and the installation conditions.
Barn — 2 Al (4)
Barn: 2 AWG aluminum, 240 V, 40 A and 260 ft one way. R = 0.319 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 40 × 260 × 0.319 / 1000 / 1 = 6.6352 V; 100 × 6.6352 / 240 ≈ 2.76467%. Check the margin for downstream circuits and the installation conditions.
Well pump building — 4 Cu (5)
Well pump building: 4 AWG copper, 240 V, 30 A and 320 ft one way. R = 0.308 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 30 × 320 × 0.308 / 1000 / 1 = 5.9136 V; 100 × 5.9136 / 240 ≈ 2.464%. Check the margin for downstream circuits and the installation conditions.
EV-ready garage — 2 Cu (6)
EV-ready garage: 2 AWG copper, 240 V, 60 A and 140 ft one way. R = 0.194 Ω/kft, 75 °C; X = 0; PF = 1. ΔV = 2 × 60 × 140 × 0.194 / 1000 / 1 = 3.2592 V; 100 × 3.2592 / 240 ≈ 1.358%. Check the margin for downstream circuits and the installation conditions.
Common Underground Feeder Mistakes
Using straight-line distance
A drawing that says 150 ft can become 180 ft to 200 ft once the trench avoids utilities, landscaping, driveways, and building entry points.
Treating burial depth as the whole code review
NEC 300.5 cover is only one part. Ampacity, grounding, neutral isolation, warning identification, physical protection, and voltage drop still matter.
Forgetting future continuous loads
A garage that only has lights today may later add a 48A EV charger, which changes both NEC 625 continuous-load sizing and voltage-drop expectations.
A Practical Underground Feeder Workflow
Use this sequence before ordering wire or closing the trench.
- 1. Calculate the load and likely future additions. Separate present load, calculated load, and realistic future loads such as EV charging, compressors, pumps, or heating equipment.
- 2. Lock the wiring method and cover requirement. Use NEC 300.5 and the chosen cable or raceway method to confirm cover depth, riser protection, and trench details.
- 3. Check ampacity and terminal temperature limits. Confirm conductor material, insulation, equipment terminals, and any derating before using voltage drop to choose a larger size.
- 4. Compare voltage drop at realistic current. Run at the expected load, not only at the breaker handle, then decide whether copper, aluminum, upsizing, or a route change is most practical.
- 5. Document the result before inspection. Record voltage, current, one-way length, conductor material, conductor size, and the calculated percent drop so the decision is easy to defend later.
Related tools and articles
Use the site tools in sequence instead of checking only one number: start with the wire size calculator, verify the governing formulas in the formulas guide, and cross-check code language in the NEC requirements article.
For adjacent scenarios, compare this topic with subpanel feeder voltage drop, detached garage feeder sizing, and the main voltage drop calculator.
FAQ
How much voltage drop is acceptable for an underground feeder?
A practical target is about 3% or less on the feeder and about 5% total feeder plus branch-circuit drop, matching the common NEC 215.2(A)(1) and 210.19(A)(1) informational-note guidance.
Does NEC 300.5 tell me what wire size to use?
No. NEC 300.5 addresses underground cover and wiring-method conditions. Wire size still comes from calculated load, ampacity tables such as NEC 310.16, terminal ratings, and voltage-drop checks.
Should I use copper or aluminum for a long underground feeder?
Both can work. Aluminum is often cost-effective for 100A to 200A feeders, but a long 180 ft to 300 ft route may need upsizing, proper terminations, and antioxidant or torque practices required by the equipment instructions.
Do detached garage feeders need four wires?
In modern NEC practice, a detached structure feeder usually uses ungrounded conductors, an insulated neutral if needed, and an equipment grounding conductor, with neutral isolated from ground at the subpanel and grounding electrodes installed as required by NEC 250.
How do I calculate underground feeder voltage drop?
Use voltage, load current, conductor material, conductor size, and one-way route length. For a 240V single-phase feeder, the current travels out and back, so the calculator accounts for the full circuit path.
When should I upsize an underground feeder?
Compare the calculated feeder loss with the selected limit and the margin required downstream. Review larger conductors or a shorter route when the margin is inadequate; motor starting, ampacity and installation requirements remain separate checks.
Planning an Underground Feeder?
If the trench route is long, the load may grow, or the conductor choice is close on voltage drop, use the contact page before backfill. A feeder review is cheaper while the route is still visible.
Related Articles
Subpanel Feeder Voltage Drop: Garage, Workshop, and Remote Panel Sizing
InstallationDetached Garage Feeder Sizing: Voltage Drop, Grounding, and NEC Rules
A practical guide to sizing detached garage feeders with voltage drop calculations, grounding rules, wire selection, and real NEC/IEC-based examples.
InstallationConduit Fill and Derating: Voltage Drop Planning for Crowded Raceways
Size raceway conductors with NEC conduit-fill limits, ampacity derating, and voltage-drop checks before a crowded conduit turns a compliant circuit into a weak one.