Case Studies
Real-world voltage drop problems and solutions from residential, commercial, industrial, and renewable energy installations. Learn from practical examples.
EV Charger Installation: 200ft Run to Detached Garage
Sizing conductors for a 48A Level 2 EV charger with a long run from the main panel to a detached garage while meeting NEC voltage drop recommendations.
The homeowner wanted to install a 48A Level 2 EV charger in their detached garage, 200 feet from the main panel. Initial calculations showed 4 AWG copper would exceed 3% voltage drop.
Upsized to 2 AWG copper conductors in PVC conduit. Verified ampacity compliance per NEC Table 310.16 and calculated final voltage drop at 2.8%.
Successful installation with 2.8% voltage drop, well within NEC recommendations. Charger operates at full power with no issues.
Manufacturing Plant: 100HP Motor Feeder Design
Designing a 480V three-phase feeder for a 100HP motor with 600ft run, considering both running and starting current.
New production line required a 100HP motor located 600 feet from the MCC. Motor starting current (6x FLA) needed to be considered for voltage drop during startup.
Used 3/0 AWG copper conductors in steel conduit. Calculated 2.1% drop at running current and 12.6% during starting. Added soft starter to limit inrush.
Motor operates smoothly with soft starter limiting starting drop to acceptable levels. Running efficiency optimized.
Data Center: Critical Power Distribution
Designing redundant power feeds for data center racks with stringent voltage tolerance requirements.
New data center build required power distribution to 200 racks with maximum 2% voltage drop to ensure stable operation of sensitive IT equipment.
Implemented 480V/277V distribution with PDUs at each row. Sized feeders for 1.5% drop maximum, used parallel 500 kcmil aluminum for main feeders.
All rack positions receive voltage within 1.8% of nominal. Zero downtime related to power quality issues.
Utility Solar: 5MW DC Collection System
Optimizing DC wire sizing for a utility-scale solar installation to maximize energy harvest while controlling costs.
Large solar farm with strings up to 500 feet from combiners. Need to balance wire cost against energy losses from voltage drop.
Developed economic optimization model comparing wire cost to lifetime energy losses. Selected 8 AWG for near strings, 6 AWG for far strings.
Optimized balance of 2.1% average DC collection losses with 15% reduction in copper costs versus uniform sizing.
Office Building: HVAC System Upgrade
Retrofitting power feeds to new high-efficiency rooftop units in an existing commercial building.
Replacing aging HVAC units with larger, more efficient models. Existing 8 AWG feeders inadequate for new 40A loads over 300ft runs.
Evaluated options: pull new 4 AWG conductors vs. installing sub-panel on roof. Sub-panel solution chosen for cost and voltage drop benefits.
New rooftop sub-panel reduced effective run to 50ft. Voltage drop from 6.2% to 1.1%. Improved compressor efficiency and lifespan.
Farm Irrigation: Pump Station Power
Powering remote irrigation pumps with long runs from the utility transformer.
Three 25HP irrigation pumps located 1,200 feet from the transformer. Standard sizing resulted in 8% voltage drop, causing motor overheating.
Installed 4/0 aluminum conductors with step-up/step-down transformers at each end. 480V transmission reduced current and losses.
Final voltage drop of 2.4% at pump locations. Motors run cool and pump efficiency improved by 8%.
Share Your Project
Have an interesting voltage drop challenge you've solved? We'd love to feature your project as a case study to help other professionals learn from real-world experience.
- Gain industry recognition
- Help fellow professionals
- Backlink to your company